I want to make an automation to close the tickets in the project "Pantalla" updated to the status "Resuelta" with more than 72 hours. I've tried some options with 1 minute to try and anything works properly.
Hi Adrian,
It should work with updated < -72h.
Kind regards,
I get the same results, even if i write 1 minute it only gives me a green check in project and status.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Adrian,
Just to be sure, you want to close issues in status Resolved that did not get an update in 72h?
Sorry for not looking more carefully.
I fear this won't work if you use the "Status changed" trigger (as this is an update).
You could do this with the free add-on Automation (Lite version) with the option "Scheduled".
Alternatively you could use Scriptrunner's Escalation Services.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
"Just to be sure, you want to close issues in status Resolved that did not get an update in 72h?" That's exactly what i want.
I've tried this and it works, the problem is that it closes the ticket automatically...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.