I've added new field "Team" to the subtasks, but can't see it on the right part of the cart info
Have a look:
The first field on the "Context fields"
But under the field "Original estimate" new added field has not appeared:
Hello @Max
Welcome to the Atlassian community.
For a Subtask the Team field will reflect the Team field setting of the subtask's parent issue. You cannot set the Team field on a Subtask independently/directly.
When you set a value for the Team field in the parent issue, then that same value will be shown, non-editable, in the subtask.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Max !!
Is your field made available on Project Screen? Could you please check your project screen configuration and check whether you made it available there and try again?
Please check your issue type screen scheme which is screen scheme related to your issue type which is Sub-Bug
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Schemes are not used for Team Managed projects.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Apologies @Max , I did not see the create field in the screenshot. Thanks for letting me know @Trudy Claspill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.