Hi community,
I created two sprints and one had been started. I couldn't start another sprint as the "Begin Sprint" button is unavailable. Is that mean only one sprint can be started at the same time?
Thanks.
Hi @Chris Zheng,
The system administrator can open Parallel Sprints as follows,allows a new sprint to be started when one is already in progress.
https://confluence.atlassian.com/jirasoftwarecloud/using-parallel-sprints-797737030.html
Wow, it works. @Ollie Guan Thank you so much!
In addition, there are some issues in one sprint, and do you know how to set up a start-time and an end-time for each issue?
Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Chris Zheng,
The start and end time of the sprint is for all the issues in the sprint,
If you want to set a different start and end date for each Issue, you can customize some datetime type fields, or you can use a plugin that implements the Gantt chart function.
e.g
https://marketplace.atlassian.com/addons/app/jira/top-selling?hosting=cloud&query=gant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.