Is the "Original Estimated Hours" relate to any issue type?
If I sum all the "Original Estimated Hours" of all issues from current sprint do I get all issue types estimations (bug, sub task, task..) or only tasks estimation?
No.
The original estimate belongs to any issue type you choose it to belong to. By default, it's the issue types at the "issue" level (because Jira Software is built for Scrum, which means estimates on sub-tasks are mostly useless). So when you look at the issues in a sprint, you'll get all the estimates for the story-level issue types.
Thanks for the quick reply.
Can I change the default so any issue type will have original estimated hours?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you change the default screens, yes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you please be more specific regarding which "screens" default should be changed?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.