Hi,
When I create a new project I have to modify the default issue screen for this new project (add time tracking) if I want to have the original estimate visible in the create issue screen. Is is possible to set this for all project types by default or at least by project type ?
Thanks for your help.
Loïc
You can also create the new project and simply change the 'Issue Type Screen Scheme' to the one used in the old project, so they'll have the same screens and that will include 'time tracking'.
That will make it easier, so you don't need to set a screen for each operation and configure them individually. It's important to point out that all screens will be the same in both projects, even those not connected to estimation.
Kind regards,
Jaime Kirch da Silveira
Atlassian Cloud Support
Once you enable "Time Tracking" to your required screens, the jira fields like Original Estimate and Remaining Estimate will be visible
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, You will need to add the field "Time Tracking" to your screens. Then you will get Original Estimate on your screens. This is not added by default.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.