Pie chard displaying Sum of original estmate per assignee in future sprint

Ivan Andonov November 8, 2023

I've seen on previous jobs that this is possible, I just can't remember how was that achieved. 

It provides huge value during planning to be able to see total original estimate in a pie chart.

this is where I am so far, but pie-chart displays issue count % per assignee not time in hrs

: project = "project" AND assignee in (Smith, Anderson) AND sprint in futureSprints("381") AND originalEstimate > 1

I get all issues tasks, subtasks and stories, but not the total estimate for the pie chart.

Any help will be appreciated.

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 8, 2023

Hi @Ivan Andonov 

There is a built-in Workload Pie Chart which does that.  Is that the one you used?

https://confluence.atlassian.com/jirasoftwareserver/gadgets-for-jira-applications-939939037.html

Kind regards,
Bill

Jagadeesh_M January 24, 2024

Hi Bill,

I do have similar requests.

Original, Remaining estimate fields are not available as statistic types in Dashboard gadgets or in other reports apart from Workload Pie Chart.

We have a JSM project requesting to have pie chart on Original estimate

Suggest an answer