Reporting - for Project managers

Jemma Phillips
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 28, 2019

Hi all

Apologies is this has been asked / answered before -but I am new to Jira :)

 

I am looking at the burnup, sprint burndown and flow diagrams on Jira.

 

In the sprint report I can see an automatically calculated Guideline (line in grey).

I wonder how I can get one (if I can get one) in the Burn up report?

 

Basically I create in excel or other my project plan and that is my baseline to deliver - I want to enter or have it calculated in Jira so we can see how far on/off track we are going or projected to go.

 

I hope that makes sense!

if anyone can help point me to an article or anything it would be appreciated!

2 answers

0 votes
Jemma Phillips
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 2, 2019

Yes I can see that is it there now - but on the Burndown I have nothing - is that because I havent applied story points?

Ste Wright
Community Champion
December 2, 2019

Hi @Jemma Phillips

Yep - if there's no estimates, it won't be able to provide you a suggested velocity for completion.

Ste

0 votes
Ste Wright
Community Champion
December 2, 2019

Hi @Jemma Phillips

Is this the burn-up in Jira Cloud Scrum Board?

If so it should be there by default - which estimate option are you using to visualise work on the burn-up chart?

Ste