Hi there
I'm struggling to understand why the status of my task which is in Done with resolution showing 'done' still won't close when I close the sprint?
I've checked the post function and it is correct, see screenshot. Not sure what to do to fix it. Stories will resolve correctly when moved to done.
Hi @Sarah,
What do you mean by "won't close when I close the sprint"? Do you get any error message when finishing the sprint?
- Manon
Hi Manon
What happens is when I try to close the sprint it says I have 27 incomplete issues, however most are sitting in 'done'
See attached
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I see! Sprints consider issues as done if they are on the far right column. If you move your Done column to the right, it should all be ok.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Sarah
By the way... looking at your board I see you have an "on hold" column/status. Is that condition a normal part of your team's workflow?
If not, instead consider removing that column/status and instead use the Blocker indicator flag for things like that.
Best regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.