Roadmap: I can't drag or edit the timeframe on the roadmap I am working on

Pau Ombao November 24, 2020

I'm just new on this and I want to know why I can't drag nor edit the timeframe on the roadmap? Will really appreciate your help. 

 

screenshot-hoolisoftware.atlassian.net-2020.11.24-18_07_56.png

1 answer

0 votes
Sajit Nair _Trundl_
Community Champion
November 24, 2020

hey @Pau Ombao ,

have you tried editing the start and end date / estimates for the story you have on there ?

Pau Ombao November 24, 2020

Hi @Sajit Nair _Trundl_ , I don't have Start and end dates. Upon checking, it's locked

Sajit Nair _Trundl_
Community Champion
November 24, 2020

@Pau Ombao, you need to be assigned to correct permissions to access that in the project. Reach out to your administrator for Schedule issues and Browse issues permission on the project and I believe it should work out

Pau Ombao November 24, 2020

Hi @Sajit Nair _Trundl_ , thank you for your effort. It's already fixed. Appreciate your answer.