Seeing a burn down based on Σ Original Estimate

kateu January 19, 2021

Hi - I would like to set my scrum board to burn down based on Σ Original Estimate. That is, as the sub-tasks of a task have time logged or are completed, I want to see this reflected in the burndown. Is this possible? 

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 20, 2021

You do not burn down on sub-tasks when you're doing Scrum, and hence Jira does not support it.

kateu January 20, 2021

But if my sub-tasks all have a original estimate, completing sub-tasks is basically logging time. If my user story has a sigma original estimate of 1 week, and a sub-task has an original estimate of 1 day, why shouldn't the remaining time be 4 days once the sub-task is closed? 

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 21, 2021

There's no "but" here.  You do not burn down on sub-tasks. Whatever estimate is put on them is irrelevant to burn down.

That is not what burn-down is for.  It is not measuring time spent or partial completion.  It measures what you deliver against what you said you would.

kateu January 23, 2021

So, the sigma original estimate is just a convenient way to add the original estimates of my sub-tasks. If I log time on my sub-tasks, there is no way to show "sigma logged time." I have to log time only on the parent ticket for remaining time to show. 