Hi All,
I want to understand if there is a way to set 'Start Date', 'End Date' for a ticket (Epic, Story, task, sub-task) in JIRA.
Thanks,
Satesh
Create date type custom fields for start and end, making sure you apply them to the right types of issue in the right projects (the easy route is to select "global")
Add them to the screens you want to use them on, and you'll be able to set, edit and report on them.