Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Show issues where time spent is greater than original estimate

Pietros
Contributor
February 28, 2017

I thought it would be easy, as JIRA supports both timeSpent and originalEstimate fields. However, it seems I cannot use these as operands:

PROJECT=A and originalEstimate < timeSpent

Is there any way how to do that, i.e. showing issues where original estimate was exceeded?

1 answer

1 accepted

1 vote
Answer accepted
Volodymyr Krupach
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2017
Eric Frank January 11, 2019

Thank you! Big help.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events