Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Some “Done” and “Cancelled” Stories from the previous Sprint show up in Current Sprint.

Samir Koirala August 19, 2022

I was viewing answers to previously asked similar question. But couldn’t fix it for my case. In my case:

1. Done and Canceled are the same columns in the far right. 
2. No sub-tasks are associated with the stories.

3. The stories were moved to the far right columns when they were completed.

Only 2 “Done” and 2 “Cancelled “ stories are appearing on the new Sprint. I did the same thing for all other Stories and they are okay. What is the anomaly in these four stories?

And how do I mark them as “Done” in Previous Sprint? They are present in my current Board on the Done Column. Any help would be appreciated!

2 answers

0 votes
Trudy Claspill
Community Champion
August 19, 2022

Take a look at the history on those issues and see when and by whom they were assigned to the sprint. Follow up on that information.

Do you have any automation rules that might have added the issues to the sprint?

Samir Koirala August 19, 2022

So after digging and comparing several stories, the only discrepancy looks like PO added two Fix Versions to the stories after they were marked as done and after the sprint was closed. Could this be the case? And how do I resolve this? 

Trudy Claspill
Community Champion
August 19, 2022

There should be an entry in the History for each issue that shows when the current sprint was added to the Sprint field for that issue. When did that happen in relation to the addition of the Fix Version values?

You should also be able to look at the Sprint Burndown for the current sprint and see when these issues were added to it. Were they present when the sprint started or where they added later?

Adding a Fix Version by itself to an issue would not automatically add the issue to a sprint in based on default functionality. Are you using any roadmapping features that correlate sprints and versions? If so maybe there is something related to that feature that caused this.

0 votes
Florian Bonniec
Community Champion
August 19, 2022

Hi

 

Is it possible that someone assign the next Sprint in the Sprint field directly from the edit screen ?

 

Regards

Samir Koirala August 19, 2022

So the Sprint ended on 8/15 and PO added two Fix Versions to the story on 8/17. The stories were marked as done. Could this be the case? 

Suggest an answer

Log in or Sign up to answer