Hi All,
I have 15 parent task which having External Estimate(custom field with number field) in backlog. Now When i create the sprint and drag that 15 parent task in sprint and checked the burndown chart i see only 10 parent task are having the events called Sprint started and rest are missing. I don't know what is the issue.
I had attached the picture for burndown chart. Please let me know any solution
In above image u can see that PDRS-14221 and PDRS-14227 are not having event type as sprint start. IT has event type as Burndown.
Please let me know if anything is needed.
Thanks,
Rohit
What other differences are there between the two issues that are not included and the ones that are?
Hi Nic,
There is no differences between two issues and rest things are same. I have attached the history of both the issues. Please check and let me know. 1st image for PDRS-14221 and the 2nd image is for PDRS-14217
Please check and let me know
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Mmm. Not sure that's the problem. What about the issue data? Anything different there (apart from text fields and the issue key of course)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.