Hello Community,
I added all the stories to my sprint and started the sprint with a planned start time later in the day (planned - 23/Mar/23 4:00 PM) but still if certain stories were added/removed from the sprint they were reflecting as spikes/drops in the sprint report even before the planned start time (planned - 23/Mar/23 4:00 PM) which was set on the sprint. How can i avoid this and is this standard behavior ? Or should I start my sprint only after all additions/deletions in terms of stories are done. Or does it work differently for JIRA server and cloud versions ?
Regards,
Jai
Hi @Jai Ganwani , yes this is expected behavior. Even though the start date is in the future, once you lock in the sprint using Start then the content is 'locked'.
Hi @Jack Brickey ! I think i have done the same thing on JIRA server edition and it used to work differently if I remember correctly. All changes made to the sprint before the planned start time were not reflected as spikes/drops on the sprint report as long as it was done before the planned start date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.