I have started sprint with 10 issues and i have manually added 35 story points but automatically there are 86 Story points which are added without knowledge.
Will the sprint Report will be created for 35 story points only or complete 35+86 story points points.
Hi @k venkat prasad ,
It looks from the report that the team are completing tickets that weren't part of the sprint. So, that maybe another problem, where the team is taking up tickets that are not part of the sprint. May need to take a look further in to the team process before starting future sprints.
The sprint report should contain the issues that were added or removed from the sprint.
-Ben