Does anyone knows the answer for below Jira issue,:
I attempt to start a new sprint , I want pull the tickets which status are not "done" and "cancel" to the new sprint. But when I operated to finish the previous sprint the alter message remind me to pull the tickets which not done to a place. I choose the next sprint , all the previous tickets have been pulled to the current sprint , "cancel" and "done" tickets are included.
If you know the answer for the above question ,it is appreciated that if you can tell me.Thanks advance.
Best wishes.
Anne
The issues that carry over into the next sprint are all the ones you have not marked as done.
Done means the last column on the board. I suspect your issues that you say are "done" and "cancel" are not in the last column when you close the current sprint.
Thanks for your answer firstly. But I am sure that the done column is the last column on my project Jira board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
And are all your "done" and "cancel" issues in that last column?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.