We have many dev teams which all have their own sprints.
I accidentally started a sprint which had at that time 9 Story Points.
Then during planning meeting we added 11 more Story Points to the sprint.
Now I want to either:
1.) change the Story Points commited
or
2.) delete the current sprint (active), create a new sprint and start that sprint with those 21 story points.
Is 1 or 2 possible???
Hi Olafur
I don't believe that 1 is possible.
For 2, create a sprint as the placeholder, move all issues into it, then delete the active one. You can then rename the placeholder
when doing this will the deleted sprint be visible in Velocity Chart?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I shouldn't think so. Yesterday I was going to say close the sprint, but deleting is better and it shouldn't then show. You should even be able to rename the new sprint to be exactly the same as the old one
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.