Start date and End date in Epic not synched with time line on Roadmaps?

Mani Kumar Chagarlamudi
Contributor
November 24, 2021

Hi,

Can Start date and End date in Epic synched with time line on Roadmaps? If I change the end date on Epic it is not reflecting on the Roadmaps time line bar and vise versa if move the time line of the epic on Roadmaps it is not being changed in the Epic.

1 answer

1 accepted

1 vote
Answer accepted
Jessica Tran
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 25, 2021

Hi Mani, 

The bars on the Roadmap reflect the default "Start date" and "Due date" fields. 

If you move the bar, the default "Start date" and "Due date" fields will be updated to reflect the new dates. 

Currently we don't support different date fields e.g "End date".

Cheers,

Jess

Mani Kumar Chagarlamudi
Contributor
November 26, 2021

That works, Thanks a lot for you help.