Hello,
I'm checking the possibility of using Roadmap as Gantt chart. I realized that stories & tasks start & due dates are not visualized on the calendar of the roadmap, neither the dependencies.
Another thing that i can't choose between different type of relation like start with, start after, finish with, etc.
Is there a solution for these issues?
Best regards,
Hi, @m_chalak. I'm afraid you'll need to use one of the Atlassian Marketplace Gantt apps for full/real Gantt chart capabilities. :(
( Full disclosure, I work for ALM Works, the makers of Structure and Structure.Gantt. Structure enables you to build work breakdown structures -- WBS -- as you see fit, and much more. Add Structure.Gantt to it and you get a complete Gantt solution. The others work more or less the same way. )
Hope this helps,
-dave [ALM Works]