Hi Community, how can I add Story Points to a "closed" sprint?
We did a backward estimation of the User Stories (after closing the relevant Sprint in Jira) and would love to add Story Points to the Sprint, but seems like there is no way to do it... or is there any?
Hi dariachanger,
Welcome to Atlassian Community!
Currently, it's not possible to modify the story points of a closed sprint, in this case, you can reopen the sprint to make this change and then mark as complete again.
- Reopening a sprint
Regards,
Angélica
Thank you for this answer as we may complete the sprint without updating storypoints for some items by mistake which impacts sprint metrics.