In our development team, we are using the JIRA scrum board and story points. We have a JIRA workflow scheme for stories with the status
"To Do" --> "In Progress" --> "Internal Review" --> "In Review" --> Done".
The storie points for the status "In Review" and "Done" should be counted as "Done" in the sprint statistics becuase there is no more work the development team.
For that we coloured the status "In Review" green and when the issue switches to this status, the screen for setting the resolution appears.
Unfortunately the story points for the status "In Review" don't count as "Done" but as "In progress". I think, there must be a bug as long as this method works in other JIRA-projects from our company.
Hi @Kristin Schmidt ,
please could you verify if "Done" status has been mapped on the last column on the right of your board settings?
Fabio
Hi @Fabio Racobaldo _Herzum_
no it wasn't. We had another column for stories with the status "Done". I deleted this column and it solved the problem.
Thank you!
Kristin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.