Yadagiri Gajjela December 1, 2020

Hi 

How does the time tracking work when we have Sub-Tasks within a Story? For instance, if I put in Original Estimate at child level this does not roll up at parent level. And, if i burn the efforts at child level it gets rolled up @ parent level. 

This does not seem to be behaving consistently. 

Also, how can i only see Parents and not children in a dashboard?

Regards

Giri

 

1 answer

1 accepted

2 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 1, 2020

If you are doing a scrum-like process with sprints, estimates and burn-down, then you do not put estimates on sub-tasks, as they are utterly pointless.

The whole point of scrum is that you are committing to deliver a set of items within a fixed time box.  The estimates live at a story level.

If you choose to break the stories up into sub-tasks, that's fine, and estimating them individually is fine if you really want to measure at that level, but the sub-tasks are utterly irrelevant to your sprint delivery and velocity.  You commit to stories, not their sub-tasks.

So, Scrum boards do not do estimates on sub-tasks because they are not of any use. 

If you're not doing scrum, then Jira does display sub-task estimates as part of the parent (it has since well before any board support was added to Jira)

Yadagiri Gajjela December 1, 2020

So, you suggest to estimate at Story level and forget estimating at sub-task level. However, burn the hours at story level?

 

Also, how do i avoid seeing sub-tasks in any dashboard or report?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 1, 2020

Yes, as that's how scrum works.

To avoid seeing sub-tasks in dashboards and reports, configure the reports and dashboards to not include them.

Yadagiri Gajjela December 1, 2020

Thank you for your response. I was thinking is there any configuration to avoid showing up sub-tasks.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 1, 2020

Exclude them from the filters you are using in the reports?

Yadagiri Gajjela December 3, 2020

Thank you

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events