Story points not counted as completed when issues moved to done

Andrew Sithers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 26, 2018

I'm missing something obvious I guess.  Our sprint tracking is set up to use Story Points as our Estimation stat, and no time tracking.

 

Given that no time tracking says 'Issues will burn down their Story Points value upon completion', why aren't my issues contributing to burn down when they're moved to done?

Thanks

1 answer

2 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2018

Is "done" in the rightmost column on the scrum board?

Francesc Arbó
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2018

Besides, when you move the issue to Done, is the resolution field of the issue completed or it's still Unresolved?

Jack Brickey
Community Champion
February 26, 2018

@Francesc Arbó, there are two ways to get your Resolution set:

  • You add the Resolution field to your 'resolve' screen which requires the assignee to select a resolution (Done, Won't do, Duplicate, etc). If you don't have a 'resolve' screen you can add one. This is best if you want the user to select the reason for marking the issue DONE.
  • You add a post function to the transition to DONE status in your workflow. This works well if you always want the resolution value to be the same, e.g. "Done"
Francesc Arbó
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2018

Hi @Jack Brickey, this is the reason why I wondered @Andrew Sithers if the issue is resolved when they transition to Done status. If it's not resolved, the story points won't be burned.

Andrew Sithers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 26, 2018

Thanks all - 

 

Workflow status is Done. Rightmost column on the board. Issues are either Fixed or Done - via a resolution screen.

:(

Jack Brickey
Community Champion
February 26, 2018

maybe seeing your burn down report and an example of a Done issue not contributing would be a good next step?