Hello, we are a construction management office and we use Jira. we have a lot of recurring work on projects that exceed the duration of a sprint. we don't want to create new tickets for these tasks that are repeated over and over again. we have created the column "recurring tasks" for them. This also works so far, because the tasks are taken over again in every sprint. as an example "construction management". Unfortunately, this falsifies the result because the sprint. it is never 100% completed at the end of the spint. Is it possible that tasks recur but are also transferred to the new locker but still recognized as completed? Greetings from Germany, Philipp
I would recommend cloning the repeatable tasks prior to closing your sprint, closing the current ones, closing the sprint, and pulling the clones into the next sprint. If you have automation for Jira, cloning your issue when it is completed is also something that can be automated if it is easier for you.
Thank you Patty for your help. I will try that!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.