I have created plan from the project, which has issue types epic, story, task, sub-task. In the plan the task issue type is not displayed under the epic where it was created. I do not filter issue types, nothing is excluded.
When I choose the hierarchy from epic to sub-taks, tasks are excluded from the view. Stories are under the epics correctly.
How do I get task issue types to be be displayed under the parent on the plan.
Please let me know when you select Epic to Story hierarchy, what view you are getting with the sceenshot.
And you have the Filter option to get the task issue type issues
Stories are correctly in the hierarchy. Tasks were created in the same way, they have parent epics.
in the project roadmap they are displayed correctly.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can define the hierarchy level as shown here
Please follow the documentation here for more reference
https://confluence.atlassian.com/advancedroadmapscloud/configuring-hierarchy-levels-998650959.html
Thanks,
Pramodh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This still does not allow you to add Tasks in below Story. You can only add Above Epic. So Advanced Roadmaps then does not display Tasks below the Story level ONLY Sub-Tasks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have resolved my issue. Tasks do come through and found under Stories. If they have an Epic Link completed then they will fall in under the Epic.
They will not be under a Story - that needs to be a Sub-Task.
So understand the flow and that works.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
First i would say to confirm that the Tasks have a parent issue. If not the plan will not show them as having one. You also could use the "Bulk Action" option by selecting the tasks you wish to assign to a parent and then update Parent.
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for your reply, tasks and stories have parent issue, were created in the same way.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You might try this documentation as well as to why you may have excluded issues.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.