Hi Tempo users
When adding a person to a Team there is a field for % commitment.
Does anyone know how that is used within Tempo?
And by this I mean if you add someone with a 50% commitment with their hours set at 40h / week, is there any correlation? If I try to plan them for more than 20 hours will it throw up any warnings?
Is the commitment value used for anything? If not, is all that it is for is to allow people when planning time to be aware of their commitment?
Thanks!
Robert
It is used when determining capacity. You can learn more here https://tempo-io.atlassian.net/wiki/spaces/THC/pages/192741544/Viewing+Team+Capacity+-+Tempo+Cloud
Just stumbled upon the same question. Guessing this is the new link as the docs have moved: https://help.tempo.io/planner/latest/viewing-capacity-per-team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.