Is it possible to change planned time to logged time in Tempo using API calls, like it is possible through UI ?
I tried adding new worklog entry with the same parameters as planned time, but it creates new entry and doesn't update the existing one.
regards,
Hi Melanie,
Planned times are not changed to worklogs in Tempo UI when you log time from them. It actually creates a worklog using the information from the planned time and does not alter it.
Best regards,
Chih from Tempo Support
Hi,
that's right.
I also want to create a work log using the information from the plan.
is it possible without going through the UI?
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Melanie,
If you are referring a single REST API call to create a worklog based on a plan, it is not possible.
The workaround would be making a REST API call to retrieve the plan and another REST API to create the worklog using the information from the previous call.
Best regards,
Chih from Tempo Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.