If I view a ticket in my next get backlog and change the status to "To Do" or "In Progress" the ticket remains in the backlog, it does not show up on my board in either the "To Do" or "In Progress" columns.
Why isn't Status synced with Column?
And, how can I sync Status with Column on a next-gen project?
This is the current functionality - issues aren't moved automatically onto the board based on status (like in Classic projects).
There are a few things that Atlassian have added:
But I appreciate the last option above is only if you're using Scrum. If you're using Kanban, there's not an automated option right now.
There are suggestions for this - I would vote / follow ideas such as JSWCLOUD-17471
Ste
Thank you for clarifying and for providing a link to vote on changing this behavior.