Tickets with "Completed" status are moving to next sprint when closing current sprint.

David
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 25, 2021

We have a workflow for our development work. The last status is "Development Complete". It is setup as a "complete" status and shows in green. My expectation is Jira recognizes these issues as done and keeps them in the current sprint when it is closed.

However, when I complete a sprint, Jira sees these issues as not complete and keeps moving them to the next sprint. What am I doing wrong?

I want to make sure that when an issue goes to "Development Complete", Jira sees them as complete.

Thanks

3 answers

1 accepted

0 votes
Answer accepted
Tessa Tuteleers
Community Champion
October 25, 2021

Hi @David ,

Jira recognizes issues as done if they are in the right most column om the sprint board.
Do you maybe have another "green" (or any) status-column at the right of your "Development Complete" on the board?

All your "closed" statuses should be in the same rightmost column of your board.

Hope this helps! 

  • Tessa
David
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 25, 2021

Tessa,

This could be the issue. We currently filter out all the "Done" statuses because it keep the board clean, but I'll update the board to include this status in the far right column and see if that helps.

Thanks

Like Tessa Tuteleers likes this
0 votes
Joe Pitt
Community Champion
October 25, 2021

The resolution must also be set

Tessa Tuteleers
Community Champion
October 25, 2021

On cloud (weirdly), no. It doesn't even have to be statuscategory done. Even issues in "to do" are marked as completed (for the sprint),  as long as they are in the rightmost column :D

0 votes
Fabian Lim
Community Champion
October 25, 2021

Hi @David

I would check the status category of the "development complete" status. Most likely is not set to "done".

Options: 

  1. Change the category status of the status. However, if other projects/boards are using the status as an in progress status they will he affected.
  2. Introduce another status such as closed to ensure that they are done after dev complete.

Cheers

David
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 25, 2021

Please see attached screenshot. The status is set to a category of "Done". I was hoping to use this status as it is more descriptive than just Done.2021-10-25_9-18-38.png

Tessa Tuteleers
Community Champion
October 25, 2021

@Fabian Lim , if the status is - as mentioned - green, it should be in the right category. On cloud, the location of the column is of importance as well (strangely enough), and not only the status or resolution.

Fabian Lim
Community Champion
October 25, 2021

Feel free to change it.  Just note that if if other projects are using the same status and don't want to identify them as "Done", their boards will be affected. Meaning, even if they want to identify them as "In Progress", their tickets will be closed after the sprint.  

Cheers.  

Monika Marko December 10, 2021

So, does it matter whether the resolution is set or not, for this problem to stop recurring? 

We have 6 statuses that have a status category "done" Also, the boards are configured to use the most far right column to map all the 6 "done" statuses...

Resolution, however is not set in any except for the Jira default: Done✅ 

After reading a lot of these posts, I have started to gather that in Jira cloud, for this problem to not occur all three conditions below, must be met: 

  1. Status category must be set to: Done (green)
  2. Resolution for the all the Done statuses except the Jira default, must be set 
  3. All the "Done' statuses, must be mapped to the far, most right column of that board, for the sprint to recognize a complete issue = done 

Could someone validate this assumption for me, please? (I am secretly hoping that I am wrong 🤞🏽😊

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events