Prasanna Deshpande September 19, 2018

A story has multiple sub-tasks

Every sub-task has original estimate

Team members are logging Time Spent and we as Remaining Time on regular basis

However for some of the Sub-Tasks the Time Logged or the remaining time is NOT considered in Burndown chart. For other tasks it's considered

 

 

For this Sub-Task below the time logged is counted in burndown

JIRA-Counted.jpg

For this Sub-Task below the time logged is NOT counted in burndown

JIRA-Not-Counted.jpg

 

2 answers

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 20, 2018

That is correct, sub-task estimates do not burn-down.

They can not, because the point of a scrum is that you either deliver a story or you do not.  There is no partial delivery, so the estimates on a sub-task are irrelevant to a burn down. 

(They can be useful in other ways, but using them causes complexity that Atlassian have chosen to ignore by saying "estimate on the story level only", where some other tools botch it, either breaking scrum or imposing often confusing methods of handling it that only work for a sub-section of their users)

Prasanna Deshpande September 21, 2018

Sub-task work logged is counted towards burndown, but it depends on how the work was logged

Use time tracking + button to log work and it's NOT counted

User ... menu ->  Log work and then it's counted

That's what we could figure based observation

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2018

That's not what I observe. 

0 votes
AhmadDanial
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 20, 2018

Hi there, Prasanna.

 

The important thing that I would like to understand first is the reason behind including sub-tasks estimation burndown charts. Is it for granular reporting or the way you keep track of the progress of a sprint as a whole? Any details that you can share will be helpful.

Meanwhile, there is a good post on this matter that discusses about sub-tasks here:

Additionally, this was also raised as a Suggestion since 2012 that you will be interested to check on:

Keep me posted soon.

Prasanna Deshpande September 21, 2018

Yes. It's for granular reporting especially when we are running small duration sprints towards end of a release.

The stories would be typically 2 days of work and tracking those with a granularity of 2-3 hours sub-tasks helps. Otherwise it could be too late for path correction.

Another case where we have a story involving both Front-End work Back-End and integration there are different members working on different areas. So with sub-tasks in burndown gives closer to reality picture on progress.

I'll have a look at those links.

Thanks for your reply.

AhmadDanial
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 21, 2018

Hi, Prasanna.

You are most welcome. Interesting use case. As @Nic Brough -Adaptavist-mentioned, the whole point of a scrum is that you either deliver a story or you do not which explains why it is excluded from Burndown chart and to remain true to the Scrum methodology.

Nevertheless, let us know if you have any further questions from the links shared.

Florin Moldoveanu
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 2, 2019

The burn down is pretty unusable from project management point of view. Stop giving self-serving propaganda to justify inaction and start listening to actual customer concerns.

Like # people like this
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 4, 2019

It's not self-serving propaganda, it's an explanation of why it is done this way.

Stop trying to justify doing it the wrong way and improve the way you think about it.