Johan Oelen January 30, 2018

I would like define a set of 12 gobal components, that can be tracked across multiple projects. In Jira  components are defined as a sub-sections of a project. 

Ist Atlassian planing something like implementing global components

2 answers

1 accepted

1 vote
Answer accepted
Thomas Deiler
Community Champion
January 30, 2018

Dear @Johan Oelen, I have no clue about the plans of Atlassian, but you can do following before waiting.

Create a custom field of type select list multiple choices and name it Global Components. Of cause the functionality is not the same, but probably it helps as long as Atlassian has implemented real Global Components.

And by the way, create a suggestion to notify Atlassian. Probably there is already one with a lot of votes.

So long

Thomas

Johan Oelen January 30, 2018

Sounds like a good idea. Thank you very much Thomas

JOhan 

Thomas Deiler
Community Champion
February 1, 2018

Dear @Johan Oelen,

was my answer fine enough to be accepted or do you need more information?

So long

Thomas

0 votes
Thomas Schlegel
Community Champion
January 30, 2018

Hi Johan, 

there is an issue for that, open since 2005. Maybe you want to vote for that:

https://jira.atlassian.com/browse/JRASERVER-8663

Jira Admin
Contributor
July 16, 2019

I'll vote on 2025 and see if they deploy it this century