Time estimation was released last year, however, I can't get point 3 to work on my team managed project. This page doesn't give much information about configurations I can change to achieve this result. My project has tickets in the current sprint and in backlog which have been estimated.
Anyone else manage to get this working?
Some more information, it seems I see story point estimate instead of original (time) estimate. I've removed story point estimate from the story, however, it's still not showing original estimate.
@Shilpa Sikotra Taylor it looks like you need to navigate to
Project settings > Features > Estimation and make sure the "Time" radio button is active.
Let me know if this helped.
Also, consider using the free Magic Estimations app for time estimates
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.