Unexpected behaviour of the Sprint Reports

Игорь Романов March 22, 2022

I was expecting one of the issues to be shown in the "Completed Tasks" category in the sprint reports.

I have the following case - an issue had created on an inactive sprint and had resolved before the sprint was finished. So I expected to see this issue in the "Completed Tasks" category in the sprint reports.

What can go wrong? Any suggestions?

1 answer

0 votes
Ollie Guan
Community Champion
March 22, 2022

Hi @Игорь Романов ,

Issue had resolved before the sprint was finished means the issue was in the current sprint but closed before the sprint due date, e.g. 3 days in advance?

Игорь Романов March 22, 2022

Hi, @Ollie Guan !

Yes, absolutely right.

Here is screenshots with examples. The issue was resolved 11 days earlier than sprint finished.

Screenshot_1.2.pngScreenshot_1.3.pngScreenshot_1.4.png

Ollie Guan
Community Champion
March 22, 2022

Hi @Игорь Романов ,

Maybe you can try query through JQL.

sprint =133 AND resolutiondate < 2022-03-21
Игорь Романов March 22, 2022

JQL works great, but I expect to see this issue in the sprint report :(

Игорь Романов March 23, 2022

Hi @Ollie Guan 

So there is no way to show my issue in the sprint report? By the way, jql is working correctly, but I still don't see my problem in the sprint report.

Suggest an answer

Log in or Sign up to answer