I was expecting one of the issues to be shown in the "Completed Tasks" category in the sprint reports.
I have the following case - an issue had created on an inactive sprint and had resolved before the sprint was finished. So I expected to see this issue in the "Completed Tasks" category in the sprint reports.
What can go wrong? Any suggestions?
Hi @Игорь Романов ,
Issue had resolved before the sprint was finished means the issue was in the current sprint but closed before the sprint due date, e.g. 3 days in advance?
Hi, @Ollie Guan !
Yes, absolutely right.
Here is screenshots with examples. The issue was resolved 11 days earlier than sprint finished.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Игорь Романов ,
Maybe you can try query through JQL.
sprint =133 AND resolutiondate < 2022-03-21
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
JQL works great, but I expect to see this issue in the sprint report :(
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Ollie Guan
So there is no way to show my issue in the sprint report? By the way, jql is working correctly, but I still don't see my problem in the sprint report.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.