Update an epic with tasks to a task with subtasks

brian.g
Contributor
September 4, 2023

How do I efficiently update an epic with tasks into a task with subtasks? I am helping a team who did not quite understand what epics were to correct their issue type usage with as little manual work as possible. 

Thanks in advance!

1 answer

1 accepted

3 votes
Answer accepted
Kai Becker
Community Champion
September 4, 2023

Hi @brian.g 

thanks for your question. Actually there is no easy way to solve this.

You will need to convert your Epic to a task and convert all Tasks to sub-tasks. For the subtasks part, you could search for all issues and then use the bulk change option to move all issues and switch the type to sub-task.

Hope this helps

brian.g
Contributor
September 4, 2023

Thanks. I first converted the tasks to subtasks (using the "Convert to subtask" function) under the epic, then converted the epic to a task (using the "Move" function). I wish this were easier, but luckily it is not something I normally do.

Like Brenda Estrella likes this