I am not working as a system administrator. but as a normal user.
I only have access to 1 project and start the csv import from the create button in the top menu bar.
I want to upload a file with tasks and subtask, under an already existing Epic.
See upload file below
Issue Type, Issue ID, Parent ID, Summary , Description , Assignee , Reporter
Task , 100 , TestEpic , Task1 , Task1 , fvb , fvb
Subtask , 1001 , 100 , Sub of task 1 , Sub of task 1, fvb , fvb
Subtask , 1002 , Task1 , sub2 of task 1,sub2 of task 1, fvb , fvb
Hi Daniel
Any update on this topic ? Where U able to create tasks under a epic via csv ?
Please share I am getting the same error
Thanks
Thanks for checking in.
I reached out to my Jira Admin and got no response.
So unfortunately no real solution here.
However I found a decent workaround:
After you upload your tasks, you can click the link to view them.
In this view, you can do a bulk change to set their Parent to the Epic you want.
It only takes maybe a few more minutes to do this extra step, so it's still pretty efficient.
For my use-case all of my tasks are generally assigned to the same Epic after I upload them, but I can imagine it being more tedious if you need to assign them to different Epics.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
With regards your CSV import,
read more about csv import here: https://confluence.atlassian.com/adminjiracloud/importing-data-from-csv-776636762.html
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ismael, Thanks for your quick answer
Actually I was looking for a field Epic Link ( I have seen when someone logged in as admin), but that field is not available for linking in my view (see screen print below)
I put a value in the parent ID of the taskm because it is mandatory. When not putting a value for parent ID for the task, an error appears> Fatal error during import: Parent Issue cannot be null
Other things are understood.
I adjusted file as suggested.
Issue Type,Issue ID,Epic link ,Parent ID,Summary ,Description ,Assignee,Reporter
Epic , 1, , ,Test Epic ,Test Epic ,fvb ,fvb
Task , 100,Test Epic , ,Task1 ,Task1 ,fvb ,fvb
Subtask , 1001, ,100 ,Sub1 ,Sub1 ,fvb ,fvb
Subtask , 1002, ,100 ,Sub2 ,Sub2 ,fvb ,fvb
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you confirm that the epic link field appears when you click the create button in JIRA?
Without this field appearing, you will not be able to import it since you are not the system admin of the instance and the basic import, follows the fields provided on the create screen.
See below from my test:
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I can con firm that the Epic Link field does NOT APPEAR
Seems like a bug to me.
I was able to create tasks and subtasks, but could not link the task to an Epic.
Same for stories. Can create but cannot link to the Epic.
In the end I used upload to create stores and sub tasks, but linked the stories manually.
why are mapping fields not same as in Supervisor Mode.
Upload of project data is a user action.
Normal user upload should work as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The reason as I mentioned is your view is the same as that of someone who clicks create on the UI. You will only be able to map fields that are on the projects create issue screen.
The Admin view supersedes this assuming the admins know what they are doing.
To fix your issue, ask your JIRA administrator to add the Epic Link field to the create issue screen of your project.
Once this is done, you should be able to import epics.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have this same issue and I have the Administrator role for my project.
Seems like a bug to me.
I could not find a way to add the Epic Link field to the create issue screen.
I am working in a next-gen project.
(Not sure if there is a cross-project kind of role that I don't have.)
I'll be manually setting the Epic from the backlog in the meantime.
It seems strange to be able to set the Epic after creation, but not before.
Additionally I don't see a "Subtask Issue Type" field either, so even if Parent Id is the correct field I'm not sure it would be usable.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here I would check first with the JIRA Administrator to ensure that the Epic Link field is on the create issue screen. If it is, then this would normally work.
It has been a while so I cannot say for certain without testing this out first.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, will do. I did not know that JIRA Administrator is different from someone who has the Admin role for a given project.
I found the "Contact Jira Administrator" page, so I'll reach out from there.
I'll post again here if I get a meaningful resolution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.