Velocity chart - Why are they restricted to last 7 sprints?

Ravi Talasila September 24, 2018

We are on cloud.

I am wondering why are these velocity charts restricted to last 7 sprints.

We need some data dating back to last 40 sprints and it seems to be impossible to fetch the data. 

Any help is appreciated.

Thank you

Ravi

1 answer

1 accepted

0 votes
Answer accepted
AhmadDanial
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 24, 2018

Hi there, Ravi.

As of now, the functionality is hard coded to show a maximum of the last 7 sprints on the report. I can't say for sure why it is limited to that amount (could potentially be performance overhead? I can't say for sure though). 

Fast forward, there is a public Suggestion for Server raised back to keep track of this:

As you can see from the official update by the Jira Server Product Management, it has been prioritized to be in the JIRA roadmap. There has not been any specific updates on JIRA Cloud so far, so I would encourage you to leave a comment on the ticket as this helps us prioritize & understand the use case of the feature request for Cloud as well.

Should you prefer to have this tracked as a separate Cloud issue, please let me know so a new ticket can be raised accordingly.

Ravi Talasila September 26, 2018

Hi Ahmad, that helps. I will leave a comment and this ticket can be closed.

Thank you

Ravi 

AhmadDanial
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 30, 2018

Hi there, Ravi.

You are most welcome. Happy to help!