Velocity for past sprints when story points have only just been added

leewarren
Contributor
April 29, 2021

We finally specified story points for issues that were completed in prior sprints. Unfortunately the velocity chart does not seem to be retroactive.  I can see from the list of issues shown below that it recorded no story points for them and yet, clicking any given issue, the detailed view for it actually shows the story points later added. Is there any way to refresh the velocity chart so that it reflects the newly added story points?

2 answers

1 accepted

1 vote
Answer accepted
Alexander Bondarev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 29, 2021

Hi, @leewarren !

If I correctly understand your question, it is impossible to re-calculate Velocity Chart. 

Because on "Sprint Start" issues were not be estimated. 

View and understand the velocity chart :

Commitment: The gray bar for each sprint shows the total estimate of all issues in the sprint when it begins. After the sprint has started, any stories added to the sprint, or any changes made to estimates, will not be included in this total. 

leewarren
Contributor
April 29, 2021

OK, thanks. I do find it amusing that even though values are entered for issues, they can't be recalculated; one would assume that velocity charts are newly regenerated each time. And indeed, there are use cases such as "we just decided the original story point estimate was wrong". I'm going to chalk this one up to Atlassian being too busy expanding their empire to concern itself with perfecting what they have. :)

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 29, 2021

Yep, you're not supposed to rewrite history.  

The correct action here is to simply document that you didn't estimate properly before executing (so people should know ignore the reported velocity, and be reassured that you're doing it better now)

leewarren
Contributor
May 1, 2021

Not a great analogy - history is often rewritten as we achieve a better understanding of it :) That's why we continually groom backlogs, and teams may better grasp their use of story points as a project proceeds. It really ought to be a team decision whether they want to update story points, and thus recalculate velocity. Not permitting this strikes me as against the spirit of agile's continuous learning ethos.

Like ren.wang likes this
0 votes
Vero Rivas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 29, 2021

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events