What is the green line in the Burndown chart?

Ricardo Filho
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2018

Hi guys!

In my Burndown chart I've a green line going up, and I've one question about it.

Is the green line the sum of all the hours worked?

Or something more specific?

Thanks!

green line.PNG

1 answer

1 accepted

1 vote
Answer accepted
Ollie Guan
Community Champion
November 29, 2018

Hi @Ricardo Filho,

In the picture above,the green line indicates the total value of the workloads recorded under all the issues in this sprint.

Ricardo Filho
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2018

Hi @Ollie Guan!

For example, If I've 8 hours estimated and burn 10 hours, that is, I burned 8 hours estimated and 2 more hours exceeded. The green line will show 10 hours. It is?

Thanks!

Ollie Guan
Community Champion
November 29, 2018

Yes, the green line shows the actual workload