When we create an EPIC in Scrum Project, how can we show EPIC crosses two Sprints in JIRA.
Hi @DEEPAK BHATIA,
I don't think there is a direct correspondence between Epic and Sprint. You can create a number of Stores that belong to an Epic. These Stores can be placed in different Sprints.
Hi Ollie,
In the link below, if you have an epic that will span multiple sprints. How do we create an epic that will span multiple sprints.
Regards
Deepak Bhatia
================================================
https://www.atlassian.com/agile/tutorials/epics
You may find it important to keep track of all incomplete issues attached to an epic. For example, if you have an epic that will span multiple sprints, you might find it useful to track the amount of work remaining over time so you can estimate when the epic will be completed.
=================================================