Hi all,
in a current sprint there are 22 issues with status "Done", and only 8 issues are incomplete. But if I click on "Complete sprint" the software says all (30) issues were incomplete.
We've changed nothing nowhere and it worked proper before. All issues that receive the status "completed" were therefore also completed in the sprint.
Was there a change within the system? Does anyone knows this problem too? Thanks for your help... Jessica
First of all, only issues in the right-most column of the board are considered completed. Also, sometimes there could be more than one Done statuses. Please check board settings.
Please check Done or resolved issues are still shown as incomplete when closing sprints for troubleshooting.
Exactly that was the problem - in the right-most column was a column for the status Hold added. After moving the "Done" column, it works proper now.
Thanks a lot for your help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you make sure that the status is in the rightmost column of the sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are there any issues that are assigned to the sprint (using a sprint field) but are not included in the Board scope (using the board filter)?
Also check your last column in the board.
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.