I find it annoying that issues for which I have created sub-tasks are placed above the regular columns titled 'other issues'.
I've become used to having issues in my 'TO DO' column, and moving them into my 'IN PROGRESS' column, etc and seeing their progress from left to right on my screen as the sprint progresses. If I create a sub-task when I need someone else to do something, then the issue is moved to a row all of its own, and I can't see that same progress with my own issue. It doesn't seem right, but I'm sure I'm simply missing the point, or doing it wrong(ly).
I'm assuming that you have your swimlanes set to Stories, which is causing this view.
Go to Board settings and then choose the Swimlanes menu item. Click on the dropdown and change it to Queries, but don't add any queries - see if that is better for you.
I had trouble finding 'Board settings', but once I had that I managed to change it as described.
On the face of it, yes, that looks better...I'll see how it works longer term.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.