Why does the "Progress Bar (Issue Count)" field in my Plan display in days (instead of #)?

Mikko Badua
Contributor
December 16, 2020

Not sure if this is a bug or I've unknowingly done something wrong, but it seems that the field, "Progress (Issue Count)" that is shown on my plan is displaying the unit as "days" instead of just showing the issue count as expected. 

 

I did the math and the actual numbers are correct (it's counting my issues in the various statuses), but the unit is oddly showing as days per below screenshot. If anyone has thoughts, I'd be all ears!

Screen Shot 2020-12-16 at 12.25.46.png

1 answer

0 votes
Vinod Ramadoss
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 23, 2020

Hi,

I suppose this is because "Original time estimate" has been selected instead of "Issue Count" as an option for "Estimation Statistic" field.

Kindly find the below link which gives more information about this feature:

Reference - https://support.atlassian.com/jira-software-cloud/docs/configure-estimation-and-tracking/

Hope this helps. 

Mikko Badua
Contributor
December 29, 2020

I don't quite think this is the case. My issue is not with any of the specific project boards. It's more about the advanced roadmaps settings. The actual project boards are all kanban boards as well, so should be counting by issue count regardless. 

The issue I'm experiencing is that the advanced roadmaps feature seems to be displaying days instead of issue counts and not finding a way to change that. Would you know if there's such a setting on advanced roadmaps settings?