Why doesn't a sprint sum estimated consider sub-tasks estimate?
I turned on "include sub-tasks" http://take.ms/y6aXg
However, issue doesn't have an estimate in the sprint http://take.ms/PYfSm
The "include sub-tasks" option there is only intended to allow you to sum the time tracking of all the subtasks into the parent issue. That checkbox won't change the estimate for the parent issue, only the way the time tracking is displayed for the parent issue. The time tracking and estimates are actually separate entities.
Configuring Estimations and Time Tracking explains this more.
When using the Burndown Chart, note that sub-task behavior can vary, depending on whether or not remaining estimate and time spent is enabled for your board.
So the way subtasks affect the burndown chart does depend on what value you have in the Board -> Configure Board -> Estimates.
Isn't this weird?
We have a parenttask with subtasks. The subtasks have estimations.
On the sprintboard we only see the maintask with estimate 0. How can we ever plan a proper sprint like this if estimates of subtasks are not taken in account?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.