Hi All,
I'd like to make a Jira Project with the following requirements and I want to generate a eazyBI/other reports,it should help me to track my work, I'd welcome the suggestions
Please suggest some best way and If any add-on could help me out I'd welcome that too.
Thanks,
Prabhu
@Hi @Prabhu Prabhakar ,
I recommend the Jira field "Due date" as the target date. For the concept of eazyBI reports, you can look at two examples on the eazyBI Demo account - https://eazybi.com/accounts/1000/dashboards/16201-forecast-and-management. The reports "Blocker Story Plan (Bar as Gantt)" and "Issue Epic Gantt Chart" could be of particular interest to you.
Best,
Roberts // support@eazybi.com
Thanks! I've a field "Business Target End Date" when the user create a ticket he'd add a certain date(approximate 5W) and each status a certain amount of time (3d,5d,7 d). Status-(Open-->Requirement Review--›Ack received)
Just looking at a report says that for example a ticket stays in a status called "'Requirement Review "Bdays of time, Open has, days Ack Received has 70).
Eg. (05/01/2022) is my "Business Target End Date" Open has 2days(Start from 09&10 of Dec 20201) and "Requirement Review" has (3days 11,12,13th Dec 2021 ) I'm still in "Requirement Review" status on 14th DEC 2021, but I supposed to be in the next status "Ack received'
Where am I? Where am I supposed to be? from my Business Target End Date?
Thanks!
Prabakaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am not confident I understand the requirement fully, but maybe the concept below can help:
You can return the number of days each issue has been in the specific Status with the measure "Days in transition status" and the respective Transition Status dimension members. In the chart above, those are represented in the stacked bars. To get the number of days an issue is also in the current status, look for the measure "Days in transition status till now" in the eazyBI Demo account report - https://eazybi.com/accounts/1000/cubes/Issues/reports/61947-issue-days-in-selected-status.
In the background, you can see the same base color areas, representing the number of days "expected" for each status. In the example above, they are hard-coded for all issues the same.
See it as a table chart below:
The Transition Status dimension affecting only one specific measure is achieved with the drill into measure by another dimension functionality - https://docs.eazybi.com/eazybi/analyze-and-visualize/create-reports#Createreports-Drillintomeasurebyanotherdimensionlevel.
Best,
Roberts // support@eazybi.com
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Prabhu Prabhakar ,
Yes! You can use the "SLA Elapsed hours" measures instead of "Days in - " for each Transition Status.
See more details on Jira Service Management measures on our documentation page - https://docs.eazybi.com/eazybi/data-import/data-from-jira/jira-service-management-custom-fields#JiraServiceManagementcustomfields-SLAmeasures.
Best,
Roberts // support@eazybi.com
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.