We are planing to run Jira (and Confluence) Datacenter on [multiple] docker instances.
It it still possible to perform a ZDU opgrade without downtime on such instances?
Hi @Normann P_ Nielsen _Netic_
Actually jira and confluence datacenter supports zero down time upgrade https://confluence.atlassian.com/adminjiraserver/upgrading-jira-data-center-with-zero-downtime-938846953.html as one of the nodes will be replying to clients while the other is upgrading.
if my answer helps please mark it as accepted.
Best Regards,
Medhat
I dont think You brought any new to the table :-)
The specifc here was "on Docker" .... so I am lokking for some form on document tation or pratical info from a user that its possible on docker.
BR,
Normann