Hi,
Some tasks in the gantt are presented with a certain duration (more than 1 day) and some gets 1 day duration.
I do not understand why there is a difference between the tasks durations, while original estimation is not filled, and the story points are the same.
I have deactivated the plugin, it didn't solve the issue.
Is there anything else to do?
Could you explain me how the basic task period is calculated in Big picture?
Thnaks,
Itamar
Hi @Itamar
Here you will find basic rules of scheduling a task - Automation & Automatic scheduling. I hope you find the articles useful.
If something stays unclear - please let me know.
Please be advised that we would like to study your case individually. Could you please raise a ticket via our Service Desk? This will allow our product specialists and developers to investigate your instance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Itamar
Could you please share a screenshot of Start & End date mapping (App configuration >> General >>Task) so I can shed more light on task period calculation?
According to the general rule, depending on the app's configuration, your tasks might get updated or recalculated during the creation of the Program. By default, the app requires two points on the timeline to generate a taskbar and determine the start and endpoints.
If a Task with no Start and/or End Dates is added to the Program's scope, the app will pick the Original Estimate value to calculate the duration and set the task's Start date to Creation date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Itamar
Thank you for sharing the screenshot. It is exactly what I meant. As I can see, the applied configuration should not influence an Original Estimate field.
The issue you described can also be caused by enabling a "Calculating tasks period based on assignee's working days' option. Could you please check a plugin's behavior once it's deactivated?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Anna-BigPicture Can you please show me how I can configure my project to allow for Start and original estimate to be the default for tasks? We don't want to assign end dates we want auto-schedule bottom up to do this please
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The ONe-Way Sync End Date Field does not show up in my app settings.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.