HI Community, 
I have a question, we have two date fields 1. Renewal date, 2.Target date to kick-off
If a renewal date is set for 1 June 2023,
then
Target date to kick-off - logic set at Renewal date - 5 months = i.e. 1 Jan 2023.

 

1 answer

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Champion
January 12, 2023

Hi @Chaitanya B ,

this can be achieved via Automation. Are you familiar with this feature? if you are an admin you can access under project settings. 

here is a rough (untested) example. The 120 is just an arbitrary number.

2023-01-12_06-27-23.jpg

Chaitanya B
Contributor
January 12, 2023

jack,
Thank you for the response,
Yes, I am  familiar with this feature, may I know the SMART VALUES for months 

Jack Brickey
Community Champion
January 12, 2023

Hi @Chaitanya B , i would refer you to this document - jira-smart-values-date-and-time so that you can get from the official source.

 

i think it would be {{date xxx.minusMonths(5)}}

but check docs.

Chaitanya B
Contributor
January 12, 2023

Thank you so much, Jack, it's working fine