Hi all, sorry fro my english
I'm using jira cloud and classic project.
During sprint we move tasks to done field and on friday close it. But tasks with done status and green don't closed and automatically added to new sprint.
While we used simple project all were good and tasks in done status made closed.
What we must change?
Hi Aleksey, can you please confirm that your "green statuses" (done category) are in the right-most column and also the Resolution field is set. If this is not the case the issues are not consider complete and will return to the backlog/next sprint.
Yes, you are right. I moved done column to most right. But here arise another question - we have rejected column and now it is not most right column and tasks from this column move to new sprint, but resolution is done.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
it needs to be in the right-most. adding multiple done will give the user the ability to drag-drop into each 'done' status separately. Alternatively, you can exclude "Rejected" status from your board's filter altogether but when the person drops into the column that maps to Rejected the issue will disappear.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amazing, this solved our issue :)!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.