"You must link this task to a project using Epic Link field" error when trying to create sub-tasks

Ahmad Sidawi
Contributor
August 4, 2023

Hi, 

 

I've been getting the 

You must link this task to a project using Epic Link field. 

 error when creating sub-tasks in a project. I've checked screens, permissions, field configuration and more and still getting the error. What am I missing?

2 answers

1 accepted

0 votes
Answer accepted
Ste Wright
Community Champion
August 4, 2023

Hi @Ahmad Sidawi 

What Issue Type are you creating these Sub-tasks under?

A screenshot of the error might be beneficial here.

Ste

Ahmad Sidawi
Contributor
August 4, 2023

A standard Task

 


Screenshot 2023-08-04 130549.pngScreenshot 2023-08-04 130532.png

Ste Wright
Community Champion
August 4, 2023

Is this Work Management of Software? And is it Company-managed or Team-managed?

Ste

Ahmad Sidawi
Contributor
August 4, 2023

Software and Company Managed :) 

Ste Wright
Community Champion
August 4, 2023

Hi @Ahmad Sidawi 

I would check Epic Link isn't a mandatory field during creation.

Usually this is via a Workflow Condition or Validator, on the create transition of the Workflow which your Sub-task uses.

If there is one, either remove it, or duplicate the Workflow and remove it from there, then assign the new Workflow to Sub-tasks.

Let us know if this works!

Ste

Ahmad Sidawi
Contributor
August 7, 2023

The workflow, thanks! Checked that and it was a condition 

Like Ste Wright likes this
0 votes
Ahmad Sidawi
Contributor
August 4, 2023

I've also checked issue hierarchy and issue types. Its only happening in one specific project.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events